Get Cooperized

Renovation

View All Section Pages

Taking Your Fitness to a Whole New Level

Committed to providing our members and guests the best in fitness, we began renovating our facilities in August 2023. Below are details about what to expect during this project.

Renovation Updates - as of April 30, 2024

The end is near...that is the end of our building renovation. Over the next few weeks we're finishing the last touches and preparing for final inspections. The following are a few tentative dates to be aware of.

  • May 6-17: Finishing touches on drywall, painting and millwork along with final inspections
     
  • Week of May 20: New space opens for use

Pickleball Coming Soon
As the building renovation wraps up, our pickleball court construction is ramping up. Temporary fencing is installed around the construction area on the east end of our tennis courts. Pending no major weather delays, the courts will be ready for play by mid-June.


Renovation Timeline

Completed late September 2023:

  • Exterior restoration of the Mansion (where our membership office is located)

Estimated completion Spring 2024:

  • Four pickleball courts

Estimated completion May 2024:

  • 6,000-square-foot expansion of the Fitness Center; will house cardio and strength training equipment

To gain the additional space, the south wall of the gym will be pushed out toward the outdoor track. The new space will include a second-floor mezzanine overlooking the fitness floor and basketball court. We will maintain the current aesthetic with large windows along the south wall.


Renderings

Future south end, 6,000 sq. ft. expansion
Cooper Fitness Center - renovation - exterior


Two-story expansion to house cardio and strength equipment
Cooper Fitness Center - renovation - interior

Parking/Entrances & Exits

We have placed signs designating additional member and spa client parking:

  • North side of the tennis courts
  • Across from the tennis courts facing Cooper Hotel II
  • North side of the Hotel II

We have also shifted staff parking to The Cooper Institute lot off Churchill.

The Willow gate entrance closest to the Fitness Center will be closed for the entirety of the project. All other entrances will remain open. The Willow/Preston Road entrance is one way—entering onto our property. You can exit through the main Preston Road gate (west side of the main Clinic building) or Churchill gate (prior to 6:30 p.m.).